fbpx

Rolleston Mine Dragline 01 Maintenance Shutdown

Project: Rolleston Mine Dragline 01 Maintenance Shutdown
Client: Glencore
Equipment: Bucyrus-Erie 2570W
Completed: July 2015
RMS Employee numbers: 16
Richglen Maintenance Services were engage to complete to change out the main suspension ropes on Dragline 01 at Rolleston Mine. Other opportunistic work such as boom repairs were also complete during the shutdown.
Highlight
No accidents or incidents
The shutdown was complete quicker than the submitted budget, this was achieved by a combined team approach. This team approach is reflective in the excellent safety and quality of the work complete.

Skills

Posted on

October 12, 2015

Submit a Comment

JOIN THE RICHGLEN TEAM TODAY!